Semi-Conductor Transformers Moving Project
Project Challenges:
Transformers at the plenum level were required to be delivered after the roof truss was constructed. This was different from the original plan of lifting equipment to position first. The project also had to be expedited.
Solution:
Jaberson was engaged to study and propose a moving solution for loads that were up to 32 times the dynamic load capacity of the building structure.
The team of planning specialists worked closely with the multi-disciplinary departments and proposed a workable solution, which was independently checked by a professional engineer. Approvals were obtained within a month and the project was executed safely and ahead of schedule.